By March 2026, 5 four-lane roads and 4 flyovers will be ready in Gorakhpur. Projects like Deoria Bypass, Nausar-Padleganj Sixlane and Khajanchi Flyover will make the city’s traffic faster, safer and jam-free.
Gorakhpur. A modern and strong network of roads and flyovers will be visible in Gorakhpur in the new year. Five major projects related to four-lane roads will be completed by March 2026, while four overbridges and flyovers will also be completed in the same period. Due to constant monitoring and review of Chief Minister Yogi Adityanath, these construction works have gained momentum.
Road connectivity of the city will change in the next 3-4 months
The internal and external traffic of Gorakhpur will become much easier with the four-lane roads and flyover projects to be completed in the next three to three and a half months. With the completion of these projects, the problem of traffic jam in the city will be reduced and traffic will become faster and safer.
Deoria bypass will become the first four lane road to be completed
Deoria Bypass Road will be the first project to be converted into four lane.
- Construction work: Start from March 2023
- Total length: 9.50 km
- Cost: Rs 399.24 crore
- Target: January 2026
- Current progress: 95 percent
Its completion will provide great relief to the external traffic of the city.
Four lane road will be built from Padleganj to Bettiahata
The 1.80 km long road from Padleganj to Bettiahata intersection via Firaq Gorakhpuri Chowk is being made four lane.
- Cost: Rs 277.78 crore
- Target: March 2026
This road will ease traffic in busy areas of the city.
Relief to Ayush University from four lane road from Bhathat to Bansthan
Bhathat to Bansthan road is being fourlaned in 11.60 km length.
- Cost: Rs 689.35 crore
- Target: March 2026
With its construction, the travel of the people coming to Ayush University will become quite convenient.
Nausadh-Padleganj will be the city’s first six lane road.
The road from Nausadh to Padleganj will be the first road in Gorakhpur, which is being converted into six lane.
- Length: 5.10 km
- Cost: Rs 297.29 crore
- Current progress: 94 percent
- Target: March 2026
District jail bypass will also be four lane
The District Jail bypass road is also being widened and strengthened into four lane.
- Length: 8.56 km
- Cost: Rs 369.04 crore
- Current progress: 96 percent
- Target: March 2026
Different units of Public Works Department are doing construction work.
- Deoria Bypass: Public Works Department, Provincial Division
- Bhathat-Bansthan, Nausadh-Padleganj, District Jail Bypass, Padleganj-Firak Gorakhpuri Chowk: Public Works Department, Construction Block-3
These overbridges and flyovers will be ready by March 2026
Major flyover and overbridge projects
- Bargadwa intersection to Nakaha Jungle-Maniram station (level crossing 5A)
Cost: Rs 152.19 crore Target: January 2026 | Progress: 97%+
- Chaurichaura-Bhopa Bazaar (level crossing 147B)
Cost: Rs 49.22 crore Target: February 2026 | Progress: 98%
- Khajanchi Chauraha Flyover
Cost: Rs 96.50 crore Target: January 2026 | Progress: 98.84%
- Nausadh-Padleganj six lane flyover and Deoria bypass connecting flyover
Cost: Rs 429.49 crore Target: January 2026 | Progress: about 80%